Bukit Chagar and the RTS Link: questions and answers
Opening date, fares, hours, passports, parking and the KTM shuttle. Each answer is marked so you can see at a glance what's settled.
Confirmed officially stated Expected announced as a target or reported Not announced no official answer yet
Opening
When does Bukit Chagar station open? Expected
The target is February 2027. It was announced on 2 October 2026 in a joint statement by Malaysia's Ministry of Transport and Singapore's LTA. It had earlier been planned for the end of 2026, then January 2027. No exact day has been given.
Why did it move to February?
To leave time for independent safety certification and final approvals. Testing and trial runs are due to finish by 31 December 2026. Both governments have said they want services running before Hari Raya 2027.
Fares and tickets
How much is the fare? Not announced
Not announced. Anthony Loke said on 20 October 2026 that fares should be announced jointly with Singapore by the end of 2026, before services start. The RM15 to RM22 (about S$5 to S$7) figures online come from a remark in February 2026, not a decision.
Will the fare be in ringgit or Singapore dollars? Not announced
Not published. The exchange rate has been mentioned publicly as one of the things being considered when setting the fare.
How do I pay? Not announced
Ticketing hasn't been confirmed. Reports suggest contactless bank cards plus the line's own system, but there's nothing official yet.
The journey
How long does the crossing take? Confirmed
About five minutes on the train, over a 4 km line. Add immigration at your departure station and the time to get to and from the two stations for your real door-to-door time.
Do I clear immigration twice? Confirmed
No. Both countries' checks are at the station you leave from, so you walk straight out when you arrive.
Do I need a passport? Confirmed
Yes. It's an international border crossing and the normal immigration rules apply. Check current requirements with the immigration authorities before you travel.
What are the operating hours? Not announced
Not published yet. First and last train times are expected around the time of the fare announcement.
How many people can it carry? Confirmed
Up to 10,000 passengers per hour in each direction.
The station
What connects to Bukit Chagar? Expected
KTM trains, buses and taxis, according to Malaysia's Transport Minister. JB Sentral is next door, and pedestrian links to KOMTAR JBCC and Coronation Square have been reported.
Is there parking? Not announced
Not announced. Wait for the operator to publish details before planning around it.
Who runs it? Confirmed
RTS Operations Pte Ltd, a joint venture of Prasarana Malaysia (52%) and SMRT Corporation (48%). The depot is at Wadi Hana in Johor Bahru.
What else changes
What happens to the KTM Shuttle Tebrau? Confirmed
It's due to stop within six months of the RTS Link starting passenger service.
Does the Causeway close?
No. Cars, motorcycles, lorries and buses keep using it. The RTS is an extra option for people crossing without a vehicle.
Will property prices near Bukit Chagar go up?
Nobody can promise that. Being close to the station will probably matter more once it opens. Whether that's already in today's prices is the question to ask before buying.
Is this site official?
No. It's an independent guide with no connection to RTS Operations, Prasarana, SMRT, Malaysia's Ministry of Transport, LTA or any other agency. Check anything important against the official announcements.
Sources: joint statement by Malaysia's Ministry of Transport and Singapore's LTA, 2 October 2026; Anthony Loke, 20 October 2026; Jeffrey Siow, 3 October 2026; RTS Operations and LTA project material. Spotted a mistake? support@bukitchagar.sg.